Revised Project Plan Due Wednesday October 26, 11:00am ET

You should use the feedback on your preliminary project plan to revise the scope of your project, and discuss any changes with your assigned TA. The goal of this assignment is to finalize the intended scope of your project based on these discussions and to outline the tasks that you will need to accomplish in order to complete your project.

Your assigned TA mentor will review your project plan and provide you with feedback on the scope and details provided in your preliminary plan. In this deliverable, you will revise your project plan based on that feedback, and any preliminary research tasks that you have completed. If there were any deficiencies or concerns noted by your TA mentor on your preliminary plan, you must address those concerns in this revised plan. If you are unsure of how to address any of these concerns or if you have addressed them, please discuss them with your TA mentor before submitting this revised plan.

We list page maximums for each section as general guidance of what we are willing to grade. Please do not feel compelled to use all of the pages provided, and remember that a diagram or table can be as expressive (or more) as a comparable amount of text.

Revised Problem Statement, User Stories and Acceptance Criteria (max 4 pages)

Your project plan should begin with a 1-3 paragraph introductory problem statement: what problem in Covey.Town does your (proposed) feature solve? Provide a paragraph (or two) that describes why you are interested in building this feature.

Given the problem statement, develop three user stories that show how a user would interact with the feature. User stories are requirements specified in the format “As a < type of user >, I want < some goal > so that < some reason >.” My conditions of satisfaction are < list of common cases and special cases that must work >. Please make sure that your conditions of satification are complete (i.e., cover all common cases) and can be turned into testable behaviors.

You should include three different user stories to describe how users will interact with your feature. Your three user stories should cover the key behavior that your feature will provide. Do not provide more than three user stories. Your problem statement and description of user stories and conditions of satisfaction should be between 2-4 pages.

This revised project plan should be a standalone document (it is OK to copy/paste from the preliminary plan in this case).

Mandatory update for all teams: Along with each condition of satisfaction, indicate its priority (high, medium, low). The priority should help refine your task breakdown.

Revised Work Breakdown (max 10 pages)

Given the project concept that you have chosen and the functionality that you expect to implement to satisfy your user stories, define a breakdown of the work that will be necessary to complete the project.

A work breakdown includes all of the tasks necessary to accomplish the project, and will be an artifact that we will refer back to throughout the project to evaluate whether you are making satisfactory progress. Consider all of the kinds of tasks that your team will need to perform, including knowledge acquisition, design, implementation, testing and documentation tasks. It is hard to say (generically) how many work items are necessary.

Each task on the work breakdown should be assigned to exactly one team member, who should provide a “T-Shirt” estimate for how long it will take (along with a justification for that estimate). Consider the dependencies between tests: perhaps an API needs to be designed and specified before implementation can begin; perhaps your development environment needs to be configured before anything else can proceed. Assign tasks to sprints considering these dependencies.

Given the preliminary nature of your project, we do not expect that you will know all of the details about precisely how to implement your feature such that you could break it down into tasks that you feel could be implemented in a day or two. However: Large tasks (those which you can not provide a responsible estimate for) must be accompanied by smaller “research” tasks that can be performed early on in the project, providing clear deadlines by which the task must either be refined into smaller tasks (based on new knowledge gathered), or reworked/abandoned. You might consider even scheduling some of these research tasks to take place during Sprint 0 (immediately after submitting this document).

For example: Consider if you were proposing the “Viewing Area” project (the individual project), without the experience of having completed it. It might be difficult to consider how to break down a task like “Implement the frontend components for sychnronized video playback” into something that you could commit to doing within a day or two. Given that this is a task that can be delayed until the end of the project (no other tasks depend on it), it would be wise to consider having some tasks early on in the project, such as: “Find react components that embed YouTube videos,” and “Implement simple video player that does not synchronize playback.” Completing these smaller tasks early would let you both demonstrate that some forward progress is being made, and also allow you to create a much more responsible estimate for how that last, otherwise insurmountably large task would take.

Be realistic, and leave time for contingencies (including the time around the midterm exam on Nov 4). Remember that you will need to have a demo prepared of your feature by 11/30 - just 6 weeks from the due date of this assignment. If you are uncertain that some tasks will be feasible, then be sure to include evaluation tasks earlier-on in the project that will allow for “go/no-go” decisions to move forward on a task or drop it.

We understand that it is quite difficult to estimate the technical complexity of a new project (as you are doing in the case of this course). We will provide you with feedback on this preliminary project plan, which you will use to produce a revised project plan (due Oct 26). Throughout the project period, teams will meet regularly with their dedicated TA Mentor, who will help track progress on a week-to-week basis and help to determine when adjustments to the project scope are needed.

Each work item should contain the following information:

  • Task to be performed
  • User story (or stories) that this task relates to
  • Team member responsible for completing the task
  • T-shirt size estimate of how long will be needed to complete the task, using the following buckets:
    • Small: Can likely be completed by one team member in one sitting of less than 3-4 hours
    • Medium: Likely to require involvement of multiple team members, over the course of 1-2 days
    • Large: Currently unable to provide a responsible estimate.
  • A brief (1-2 sentence max) justification of how you reached the size estimate of the task
  • Milestone for delivering the task, chosen from one of the following:
    • Sprint 0: Oct 12-Oct 26
    • Sprint 1: Oct 27-Nov 2 (Sprint 1 is just a single week)
    • Sprint 2: Nov 3-Nov 16
    • Sprint 3: Nov 17-Nov 30

Your work breakdown should take the format of a simple textual list.

Mandatory update for all teams: Even if your work breakdown is entirely unchanged compared to the preliminary plan, please be certain to include updates on all “sprint 0” tasks (those which were scheduled to be completed before the due date of this revised plan). Many teams included research/learning tasks in the first week to help inform the rest of the work breakdown: you should be certain to revise your work breakdown based on what you have learned so far.

Changelog:

  • 10/21: Updated details about conditions of satisfaction (being testable and include priority). Also updated the grading breakdown.

Submission

Your revised project plan should be submitted as a single PDF in GradeScope to the assignment “Revised Project Plan.” Each team submits a single document to GradeScope: when uploading the submission, GradeScope will ask you who your teammates are, and then will associate this submission with every member of your team. Be sure to tag your team mates. This assignment is due Oct 26 at 11am.

Grading

The revised project plan will account for 10% of your project grade, and will be graded out of 100 points. The grading of the revised project plan is further broken down as follows:

Introductory problem statement (5 points):

  • Receive full marks if there is a narrative consisting of 4-10 sentences that describes a specific problem that your project aims to solve.
  • Receive partial credit if the narrative is present, but does not describe a problem that the project aims to solve

User stories (45 points):

Each of the three user stories will account for 5% of your grade on this assignment and graded as follows:

  • Receive full marks if:
    • The user story fits the problem statement
    • The user story satisfies the INVEST criteria for good user stories (construed quite broadly)
    • The user story includes conditions of satisfaction that cover the “normal” expected behavior of the feature, and any relevant error cases
    • Conditions of satisfaction can be turned into Testable behaviors
    • Conditions of satisfaction are prioritized

Work breakdown (50 points):

Your work breakdown will be evaluated holistically on the following rubric:

Coverage of tasks needed (20 points):

Receive full marks if the work breakdown includes all (reasonably expected) tasks to implement your feature, considering these kinds of tasks:

  • Background research
  • Design of interfaces and data types
  • Deployment of third-party services
  • Implementation
  • Testing
  • Documentation

It is not possible to state generically for all projects whether all of the above types of tasks are necessary. However, we believe that this list is exhaustive (we do not expect other kinds of tasks).

Assignment of tasks (5 points):

Receive full marks if:

  • Each element on the work breakdown is assigned to one team member
  • The distribution of tasks of each size are roughly similar between the whole team (no single person is assigned significantly more or fewer tasks of one size)

Sizing of tasks (20 points):

Receive full marks if each element on the work breakdown:

  • Has a size estimate (small, medium, or large) that is provided by the team member assigned the task.
  • Has a responsible justification for that estimation
  • Every “large” task:
    • Is accompanied by a reasonable explanation of why the team is unnable to provide a responsible estimate
    • Is accompanied by at least one small or medium task, scheduled well-before the “large” task is due to be completed. We would expect that most of these research tasks are scheduled to sprint 0, or perhaps sprint 1.

Scheduling of tasks (5 points):

Receive full marks if each element on the work breakdown:

  • Is assigned to a sprint
  • There are no obvious constraint violations (tasks that logically must happen before others should be scheduled before them)
  • There are no “Large” tasks scheduled in sprint 0
  • Tasks scheduled to be completed before 10/26 have an update as to their status, and the work breakdown is updated to reflect the result of these tasks.